Municipalities can submit applications for funding for wall boxes. The following points must be observed:
- The deadline for implementation is 1 year after the application.
- The subsidy is up to €900 per charging point.
- The minimum subsidy amount is €9,000 with at least 10 charging points.
- The charging power can be 22 kW.
- The charging stations are not intended for public access.
With ten charging points, exactly €9000 can be funded, but only 70% of the total costs.
The total investment (purchase + installation) must therefore be at least €12857.14.
For more than 10 Charging points are then funded with 70% of the actual investment sum up to a maximum rate of €900 per charging point.